Data center facility

Compass Red Oak Campus Expansion (buildings 6-8)

Compass Datacenters · Red Oak · 481 Austin Boulevard, Red Oak, TX. Every figure below is individually sourced and dated.


Part of the tracked campus Compass Datacenters Red Oak Campus (DFW III).

The story of Compass Red Oak Campus Expansion (buildings 6-8)inherited from campus Compass Datacenters Red Oak Campus (DFW III)
Announced capex
$300M
Cooling
Air-cooled, N+1 redundancy
Derived
Cost per MW
$833K/MW

Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.

In clusterTexas(606)

The deal

Inherited from campus Compass Datacenters Red Oak Campus (DFW III).

developer
Compass Datacenters · Entity Compass Datacenters DFW III, LLC
utility
Hilco Electric Cooperative · Grid power provider to the Red Oak (DFW III) campus at 300 Houston School Road; TCEQ Federal Operating Permit O4679

Financial structure

Inherited from campus Compass Datacenters Red Oak Campus (DFW III).

DFW III expansion (up to 3 additional buildings)
$300M. Combined construction cost of up to three more facilities announced Sept 2024 journalist report

Investment, workforce and specs

Inherited from campus Compass Datacenters Red Oak Campus (DFW III).

Cooling
Air-cooled, N+1 redundancy source

Power

Inherited from campus Compass Datacenters Red Oak Campus (DFW III). Live grid demand and drought overlay only render on the campus page.

Power source
grid
Grid operator
ERCOT
Interconnection
Water
Closed-loop water-cooling system that is not connected to the city utility line and, per city staff, uses less water annually than a Walmart Supercenter.

Facility record

planned

Status

hyperscale

Type

Red Oak

Location

251,815 sqft

Building

Oncor

Serving utility

On the data center map

Free to use on your site, with a link back to DEPLOY.

Construction evidence

Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.

Delivery paceAnnounced Q2 2025 · live Q1 2026 · 7 mo build

2018-08-25Contains modified Copernicus Sentinel data 2018
2020-08-19Contains modified Copernicus Sentinel data 2020
2022-06-20Contains modified Copernicus Sentinel data 2022
2024-09-10Contains modified Copernicus Sentinel data 2024
2025-09-10Contains modified Copernicus Sentinel data 2025

Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones inherited from campus Compass Datacenters Red Oak Campus (DFW III). How we source and verify it: satellite construction evidence.

Evidence

Each fact traces to a source. This is what a verified record looks like next to an unsourced directory listing.

  • buildingSqft: 251815 (reported) · source · Building 2 of the existing Red Oak campus
  • record: Compass Red Oak Campus Expansion (buildings 6-8) (reported) · source
  • servingUtility: Oncor (reported) · source
  • status: planned; three additional facilities added to campus ($300M) (reported) · source
  • streetAddress: 481 Austin Boulevard, Red Oak, TX (reported) · source

Timeline

  1. Aug 2026
    First recorded
    Added to the DEPLOY registry as a sourced facility record
  2. Aug 2026
    Current: planned

Facility-tier record. For campus-scale announced-vs-energized tracking see the data center index. DEPLOY is neutral infrastructure: what is claimed, what is verified, and when.

Common questions

What is Compass Red Oak Campus Expansion (buildings 6-8)?
Compass Red Oak Campus Expansion (buildings 6-8) is a data center facility record on the DEPLOY registry, in Red Oak. Every fact on the record is individually sourced and dated.
Who operates Compass Red Oak Campus Expansion (buildings 6-8)?
Compass Datacenters operates Compass Red Oak Campus Expansion (buildings 6-8), per the sourced record on the DEPLOY registry.
Is Compass Red Oak Campus Expansion (buildings 6-8) operating?
Compass Red Oak Campus Expansion (buildings 6-8) is recorded as planned on the DEPLOY registry. Each figure traces to a source.
How verified is the data on Compass Red Oak Campus Expansion (buildings 6-8)?
A human editor has reviewed this record for the indexed registry. Every rendered fact shows its source: this is what a verified record looks like next to an unsourced directory listing.

Deploy Watch

Track Compass Red Oak Campus Expansion (buildings 6-8) on Deploy.

We notify you when operating status, capacity, or the operator changes against a sourced record.

Cite this page

DEPLOY. (2026). Compass Red Oak Campus Expansion (buildings 6-8): data center facility record. Retrieved August 29, 2026, from https://registry.deploy.report/datacenters/facilities/compass-red-oak-expansion-ellis-county-tx

More citation formats (MLA, Chicago, BibTeX) →
CC BY 4.0

The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.

Machine-readable surfaces