Data center campus
Compass Datacenters Red Oak Campus (DFW III)
Compass Datacenters' Red Oak campus in Ellis County holds TCEQ operating permits (Red Oak Datacenter / DFW III) and is planned for ~360 MW across ~10 buildings on 300 acres; five buildings came online 2024-2025 fully leased to a single tena
Partially energized · Private land · ERCOT · Red Oak, Texas, United States
Capacity: announced vs energized
Announced
not recorded
Contracted
not recorded
Under construction
not recorded
Energized
0.36 GW
reported
| Source | ||||
|---|---|---|---|---|
| Energized | 0.36 GW | 2026-01-01 | reported | permit |
The deal
- developer
- Compass Datacenters · Entity Compass Datacenters DFW III, LLC
Power
- Power source
- grid
- Grid operator
- ERCOT
- Interconnection
Sources
- Compass Datacenters Lands Refi on 5 Red Oak Facilities to Add Three More
- DFW - Red Oak (facility profile)
43a07716-a21a-44dc-96de-1421aa5d186b · Tracked with DEPLOY's verified-vs-claimed methodology. Announced numbers are claims, not built capacity.