Data center facility
Eagle Mountain Data Center
Meta · Eagle Mountain · 1275 North Community Circle, Eagle Mountain, UT. Every figure below is individually sourced and dated.
Part of the tracked campus Meta Eagle Mountain Data Center Campus.
- Announced capex
- $1.5B
- Jobs
- 300 permanent reported
- Grid
- WECC · Grid connected and operating: the campus is served by Rocky Mountain Power and is serving traffic. Meta is bringing more than 800 MW of new solar onto that grid through nine projects across Iron, Tooele and Carbon counties, carrying about $260 million of local investment.
- Cost per MW
- $833K/MW
- Cost per job
- $5M per permanent job
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterUtah(67)
The deal
Inherited from campus Meta Eagle Mountain Data Center Campus.
- utility
- Rocky Mountain Power (PacifiCorp) · Schedule 34 renewable tariff
- operator
- Meta Platforms
- developer
- Excelsior Energy Capital · Owner/developer of the Faraday Solar project supplying the Meta campus via a 20-year renewable PPA (acquired the project from Parasol/Clenera in 2023).
Financial structure
Inherited from campus Meta Eagle Mountain Data Center Campus.
- Meta cumulative campus investment
- $1.5B. Total capital investment cited at 2022 Phase 3 expansion toward ~4.5M sq ft campus. journalist report
Investment, workforce and specs
Inherited from campus Meta Eagle Mountain Data Center Campus.
Power
Inherited from campus Meta Eagle Mountain Data Center Campus. Live grid demand and drought overlay only render on the campus page.
- Power source
- grid
- Grid operator
- WECC
- Interconnection
- Grid connected and operating: the campus is served by Rocky Mountain Power and is serving traffic. Meta is bringing more than 800 MW of new solar onto that grid through nine projects across Iron, Tooele and Carbon counties, carrying about $260 million of local investment.
- Water
- Meta funds water restoration equal to 200% of the facility's consumption; in-house designs stated ~80% more water-efficient than industry average.
Faraday Solar, 0.69 GW solar, Energized. 685.3 MWdc; 20-year PPA via Rocky Mountain Power Schedule 34.
Spanish Fork (Mapleton) to Mercer 345 kV transmission line, grid, Announced. 45-mile 345 kV line proposed by Rocky Mountain Power (Aug 2025) to add capacity serving Utah County load growth; delivers to the Mercer substation (built 2019 to serve the Meta campus).
Facility record
On the data center map
Construction evidence
Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.
Delivery paceAnnounced Q4 2025 · live Q1 2025 · -10 mo build
Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones inherited from campus Meta Eagle Mountain Data Center Campus. How we source and verify it: satellite construction evidence.
Evidence
Each fact traces to a source. This is what a verified record looks like next to an unsourced directory listing.
Timeline
- Aug 2026First recordedAdded to the DEPLOY registry as a sourced facility record
- Aug 2026Current: operating
Facility-tier record. For campus-scale announced-vs-energized tracking see the data center index. DEPLOY is neutral infrastructure: what is claimed, what is verified, and when.
Common questions
What is Eagle Mountain Data Center?
Who operates Eagle Mountain Data Center?
Is Eagle Mountain Data Center operating?
How verified is the data on Eagle Mountain Data Center?
Deploy Watch
Track Eagle Mountain Data Center on Deploy.
We notify you when operating status, capacity, or the operator changes against a sourced record.
Cite this page
DEPLOY. (2026). Eagle Mountain Data Center: data center facility record. Retrieved August 30, 2026, from https://registry.deploy.report/datacenters/facilities/meta-eagle-mountain-ut
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/facilities/meta-eagle-mountain-ut.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/facilities/meta-eagle-mountain-ut
- Data documentation: /data
- Query this programmatically: Deploy MCP