Data center facility

Eagle Mountain Data Center

Meta · Eagle Mountain · 1275 North Community Circle, Eagle Mountain, UT. Every figure below is individually sourced and dated.


Part of the tracked campus Meta Eagle Mountain Data Center Campus.

The story of Eagle Mountain Data Centerinherited from campus Meta Eagle Mountain Data Center Campus
Announced capex
$1.5B
Jobs
300 permanent reported
Grid
WECC · Grid connected and operating: the campus is served by Rocky Mountain Power and is serving traffic. Meta is bringing more than 800 MW of new solar onto that grid through nine projects across Iron, Tooele and Carbon counties, carrying about $260 million of local investment.
Derived
Cost per MW
$833K/MW
Cost per job
$5M per permanent job

Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.

In clusterUtah(67)

The deal

Inherited from campus Meta Eagle Mountain Data Center Campus.

utility
Rocky Mountain Power (PacifiCorp) · Schedule 34 renewable tariff
developer
Excelsior Energy Capital · Owner/developer of the Faraday Solar project supplying the Meta campus via a 20-year renewable PPA (acquired the project from Parasol/Clenera in 2023).

Financial structure

Inherited from campus Meta Eagle Mountain Data Center Campus.

Meta cumulative campus investment
$1.5B. Total capital investment cited at 2022 Phase 3 expansion toward ~4.5M sq ft campus. journalist report

Investment, workforce and specs

Inherited from campus Meta Eagle Mountain Data Center Campus.

Capex
$1.5B source
Construction jobs
1,200 source
Permanent jobs
300 source

Power

Inherited from campus Meta Eagle Mountain Data Center Campus. Live grid demand and drought overlay only render on the campus page.

Power source
grid
Grid operator
WECC
Interconnection
Grid connected and operating: the campus is served by Rocky Mountain Power and is serving traffic. Meta is bringing more than 800 MW of new solar onto that grid through nine projects across Iron, Tooele and Carbon counties, carrying about $260 million of local investment.
Water
Meta funds water restoration equal to 200% of the facility's consumption; in-house designs stated ~80% more water-efficient than industry average.

Faraday Solar, 0.69 GW solar, Energized. 685.3 MWdc; 20-year PPA via Rocky Mountain Power Schedule 34.

Spanish Fork (Mapleton) to Mercer 345 kV transmission line, grid, Announced. 45-mile 345 kV line proposed by Rocky Mountain Power (Aug 2025) to add capacity serving Utah County load growth; delivers to the Mercer substation (built 2019 to serve the Meta campus).

Facility record

operating

Status

hyperscale

Type

Meta

Operator

Rocky Mountain Power

Serving utility

On the data center map

Free to use on your site, with a link back to DEPLOY.

Construction evidence

Dated satellite imagery of the site itself, oldest to newest, with the campus milestones that landed in each window. This is what the site looked like from orbit while announcements, permits, and energizations were dated into our ledger, so bare land, grading, and building mass tell their own story alongside the paper trail. Sentinel-2 true color, 10 m resolution, cloud-free scenes; click any frame to expand it.

Delivery paceAnnounced Q4 2025 · live Q1 2025 · -10 mo build

2018-06-12Contains modified Copernicus Sentinel data 2018
2020-09-14Contains modified Copernicus Sentinel data 2020
2022-09-09Contains modified Copernicus Sentinel data 2022
2024-09-06Contains modified Copernicus Sentinel data 2024
2025-05-31Contains modified Copernicus Sentinel data 2025

Dated Sentinel-2 imagery, gated to hand-verified site coordinates. Milestones inherited from campus Meta Eagle Mountain Data Center Campus. How we source and verify it: satellite construction evidence.

Evidence

Each fact traces to a source. This is what a verified record looks like next to an unsourced directory listing.

  • record: Eagle Mountain Data Center (reported) · source
  • servingUtility: Rocky Mountain Power (reported) · source
  • status: operating (reported) · source
  • streetAddress: 1275 North Community Circle, Eagle Mountain, UT (reported) · source · 7-building campus

Timeline

  1. Aug 2026
    First recorded
    Added to the DEPLOY registry as a sourced facility record
  2. Aug 2026
    Current: operating

Facility-tier record. For campus-scale announced-vs-energized tracking see the data center index. DEPLOY is neutral infrastructure: what is claimed, what is verified, and when.

Common questions

What is Eagle Mountain Data Center?
Eagle Mountain Data Center is a data center facility record on the DEPLOY registry, in Eagle Mountain. Every fact on the record is individually sourced and dated.
Who operates Eagle Mountain Data Center?
Meta operates Eagle Mountain Data Center, per the sourced record on the DEPLOY registry.
Is Eagle Mountain Data Center operating?
Eagle Mountain Data Center is recorded as operating on the DEPLOY registry. Each figure traces to a source.
How verified is the data on Eagle Mountain Data Center?
A human editor has reviewed this record for the indexed registry. Every rendered fact shows its source: this is what a verified record looks like next to an unsourced directory listing.

Deploy Watch

Track Eagle Mountain Data Center on Deploy.

We notify you when operating status, capacity, or the operator changes against a sourced record.

Cite this page

DEPLOY. (2026). Eagle Mountain Data Center: data center facility record. Retrieved August 30, 2026, from https://registry.deploy.report/datacenters/facilities/meta-eagle-mountain-ut

More citation formats (MLA, Chicago, BibTeX) →
CC BY 4.0

The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.