Data center campus

Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus)

Google Visakhapatnam AI Hub is an AI data center campus developed by AdaniConneX in Andhra Pradesh, Visakhapatnam. 1 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Under construction · AdaniConneX · Private land · other · Visakhapatnam, Andhra Pradesh, India


Capacity: announced vs energized

Announced-to-energized gap: 1 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Promised online: 2026-04-28. 4 months past the claimed date, with no energized capacity on record. Claimed by Google (source).

Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus) capacity claims
Source
Announced1 GW2026-06-01reportedjournalist report

Key facts

1 GW

Announced

0 GW

Energized

AdaniConneX

Developer

India

Location

other

Grid

1 GW

Announced-to-energized gap

On the data center map

No mappable coordinate is recorded for Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus) yet. Location: Visakhapatnam.

The deal

operator
Google · Anchor; deploys full AI stack at the hub
developer
AdaniConneX · 50:50 JV of Adani Enterprises and EdgeConneX; infrastructure developer
operator
Nxtra by Airtel (Bharti Airtel) · Connectivity / subsea cable ecosystem partner
land owner
Government of Andhra Pradesh · Allotted 480 acres (Visakhapatnam / Anakapalli districts) to Adani Infra

Power

Power source
mixed
Grid operator
other
Interconnection

Why here

Google Visakhapatnam AI Hub sits on private land in Andhra Pradesh, Visakhapatnam. It connects to the other grid, draws on mixed power. This siting summary is composed from the record's held fields, not speculation; see methodology.

Financial structure

Google investment in Andhra Pradesh, 2026-2030
$15B press release

Regulatory paper trail

The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.

Investment, workforce and specs

Construction jobs
tens of thousands of jobs in technology, construction and clean energy source

Timeline

  1. Aug 2026
    party added
    land_owner: Government of Andhra Pradesh
  2. Aug 2026
    Current: Under construction

Sources

b0ab3fbf-df7d-4bcd-bc2e-a5532cf92542 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.

Head-to-head

Common questions

What is Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus)?
Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus) is an AI data center campus tracked on the DEPLOY registry, located in Visakhapatnam. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.
How much power will Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus) use?
Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus) has 1 GW of announced capacity on the DEPLOY registry; no energized capacity is yet recorded. Each figure is individually dated and sourced.
Who is building Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus)?
AdaniConneX is recorded as a party to Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus) on the DEPLOY registry.
Is Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus) operating yet?
As of the most recent verification on the DEPLOY registry, Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus) is under construction. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.
How verified is the data on Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus)?
A human editor has reviewed this record for the indexed registry. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

Deploy Watch

Track Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus) on Deploy.

We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.

Cite this page

DEPLOY. (2026). Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus): AI data center campus record. Retrieved August 20, 2026, from https://registry.deploy.report/datacenters/google-visakhapatnam-ai-hub