Data center campus

Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus)

Google Visakhapatnam AI Hub is an AI data center campus developed by AdaniConnex in Andhra Pradesh, Visakhapatnam. 1 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Under construction · AdaniConnex · Private land · other · Visakhapatnam, Andhra Pradesh, India


Capacity: announced vs energized

Announced-to-energized gap: 1 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Promised online: 2026-04-28. 5 months past the claimed date, with no energized capacity on record. Claimed by Google (source).

Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus) capacity claims
Source
Announced1 GW2026-06-01reportedjournalist report

Key facts

1 GW

Announced

0 GW

Energized

AdaniConnex

Developer

India

Location

other

Grid

1 GW

Announced-to-energized gap

Reported facts

Structured facts sourced from citations already on this record. Each fact traces to a source in the References section below.

Groundbreaking / partners (company)
Google broke ground Apr 28 2026 at Tarluvada, Visakhapatnam (Vizag), Andhra Pradesh on its India AI hub, developed with AdaniConneX and Nxtra by Airtel (Google Cloud Press Corner, Apr 28 2026)
Investment envelope (company)
Company materials frame the hub as part of Google's approximately $15 billion investment over five years (2026-2030) in India's AI ecosystem, called Google's largest investment in India's digital future to date (Google Cloud Press Corner, Apr 28 2026; Adani, Oct 14 2025)
Campus structure (company)
Google describes India's first gigawatt-scale AI hub as three data center campuses, with AdaniConneX and Nxtra by Airtel leading construction of buildings and connecting infrastructure (Google Cloud Press Corner, Apr 28 2026)
Scale claim (partner quote)
At groundbreaking, Adani Group's Jeet Adani said what is being built in Visakhapatnam is nearly 1 GW in a single location (Google Cloud Press Corner, Apr 28 2026)
Connectivity / clean energy (company)
Google ties the hub to America-India Connect fiber expansion, three subsea cables landing in Visakhapatnam (per Indian IT Minister remarks at the event), and a long-term clean energy strategy to bring new clean supply to the grid toward India's 500 GW non-fossil goal by 2030 (Google Cloud Press Corner, Apr 28 2026)
Site acreage (trade press)
Trade press reports the three sites span about 266.6 acres in Tarluvada, 160 acres in Adivivaram, and 174.8 acres in Rambilli-Achyutapuram, with commissioning aims around July 2028. Treat acreage splits and exact energization dates as reported, not company-filed MW schedules (Data Center Dynamics, Apr 28 2026)

On the data center map

Every tracked data center is on this map, centered on Google Visakhapatnam AI Hub. Pan or zoom out to see how close rivals are building.

Free to use on your site, with a link back to DEPLOY.
The story of Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus)
Announced capex
$15B
Land owner
Government of Andhra Pradesh
Derived
Cost per MW
$15M/MW

Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.

In clusterAndhra Pradesh(3)

The deal

operator
Google · Anchor; deploys full AI stack at the hub
developer
AdaniConneX · 50:50 JV of Adani Enterprises and EdgeConneX; infrastructure developer
operator
Nxtra by Airtel (Bharti Airtel) · Connectivity / subsea cable ecosystem partner
land owner
Government of Andhra Pradesh · Allotted 480 acres (Visakhapatnam / Anakapalli districts) to Adani Infra
developer
AdaniConnex

Power

Power source
mixed
Grid operator
other
Interconnection

Why here

Google Visakhapatnam AI Hub sits on private land in Andhra Pradesh, Visakhapatnam. It connects to the other grid, draws on mixed power. This siting summary is composed from the record's held fields, not speculation; see methodology.

Financial structure

Google investment in Andhra Pradesh, 2026-2030
$15B press release

Regulatory paper trail

The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.

Investment, workforce and specs

Construction jobs
tens of thousands of jobs in technology, construction and clean energy source

Timeline

  1. Aug 2026
    party added
    land_owner: Government of Andhra Pradesh
  2. Oct 2026
    Current: Under construction

Sources

b0ab3fbf-df7d-4bcd-bc2e-a5532cf92542 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.

Head-to-head

Common questions

What is Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus)?
Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus) is an AI data center campus tracked on the DEPLOY registry, located in Visakhapatnam. DEPLOY records its capacity as a dated, sourced ledger: announced gigawatts versus actually energized gigawatts, never a press-release total.
How much power will Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus) use?
Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus) has 1 GW of announced capacity on the DEPLOY registry; no energized capacity is yet recorded. Each figure is individually dated and sourced.
Who is building Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus)?
AdaniConnex is recorded as a party to Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus) on the DEPLOY registry. The full party list, with each role, is on the record.
Is Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus) operating yet?
As of the most recent verification on the DEPLOY registry, Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus) is under construction. DEPLOY tracks the lifecycle from announced through energized, so the current state reflects sourced evidence, not the original announcement.
How verified is the data on Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus)?
A human editor has reviewed this record for the indexed registry. Every capacity figure is an append-only, dated claim resolved to the highest-evidence tier; superseded claims are kept but excluded from the current view.

Deploy Watch

Track Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus) on Deploy.

We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.

Cite this page

DEPLOY. (2026). Google Visakhapatnam AI Hub (Adani-Google Data Centre Campus): AI data center campus record. Retrieved October 4, 2026, from https://registry.deploy.report/datacenters/google-visakhapatnam-ai-hub