Data center campus
Nxera Batam (BDC1)
Nxera Batam is a tracked AI data center campus in Batam. Joint venture with Medco Power Indonesia; positioned as Singapore-adjacent capacity leveraging cross-border connectivity. Groundbreaking 2024.
Capacity: announced vs energized
| Source |
|---|
Key facts
Reported facts
Structured facts sourced from citations already on this record. Each fact traces to a source in the References section below.
- IT capacity
- 51 MW (Phase 1 announced IT capacity; site master plan cited up to 200MW)
- Kabil Batam JV / 51 MW campus plan (primary Nxera)
- Nxera/Singtel's Dec 21 2022 release announces a strategic partnership with Telkom and Medco Power for Singtel's first Indonesia data centre, with groundbreaking at Kabil Industrial Estate on Batam's eastern seaboard. The campus is described as three phases on an 8-hectare site with total capacity of 51 MW when fully completed and an initial phase of approximately 20 MW, majority-owned by Telkom with Singtel and Medco Power as minority shareholders. Frame MW as 2022 announcement plan (Nxera / Singtel, Dec 21 2022)
- BTM-1 topping / 18 MW initial IT load (primary NeutraDC)
- NeutraDC's Oct 30 2025 topping-off release for NeutraDC Nxera Batam's first building (BTM-1) in Kabil Industrial Estate states an initial IT load capacity of 18 MW, scalable up to 54 MW in subsequent phases, purpose-built for AI and cloud demand. Frame the 18/54 MW figures as the JV's updated construction-era claims (distinct from the earlier 51/20 MW Dec 2022 plan) (NeutraDC, Oct 30 2025)
- Telkom-Nxera-Medco / SIJORI gateway framing (primary NeutraDC)
- The same NeutraDC release positions the Batam campus within the SIJORI growth triangle (Singapore-Johor-Riau) as a regional gateway, with partners Nxera (Singtel) and Medco, and describes the facility as strengthening Indonesia's digital infrastructure for AI, cloud, and big data. Treat regional-hub language as developer positioning (NeutraDC, Oct 30 2025; Nxera / Singtel, Dec 21 2022)
On the data center map
No mappable coordinate is recorded for Nxera Batam (BDC1) yet. Location: Batam.
The deal
- developer
- Nxera
Power
- Power source
- mixed
- Interconnection
Why here
Nxera Batam is in Batam. It draws on mixed power. This siting summary is composed from the record's held fields, not speculation; see methodology.
Sources
- Nxera Batam (BDC1) — singtel-nxera facility
- Singtel enters Indonesia data centre market
- TelkomGroup Tops Off NeutraDC Nxera Batam Hyperscale Data Center
a3956560-b4a6-41b7-b20c-f7212b4e86f3 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Nxera Batam (BDC1)?
Who is building Nxera Batam (BDC1)?
Is Nxera Batam (BDC1) operating yet?
How verified is the data on Nxera Batam (BDC1)?
Deploy Watch
Track Nxera Batam (BDC1) on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Nxera Batam (BDC1): AI data center campus record. Retrieved October 11, 2026, from https://registry.deploy.report/datacenters/singtel-nxera-nxera-batam
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/singtel-nxera-nxera-batam.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/singtel-nxera-nxera-batam
- Data documentation: /data
- Query this programmatically: Deploy MCP