Data center campus
YTL Green Data Center Park
YTL Green Data Center Park is an announced AI data center campus. 0.50 GW of capacity has been announced; 0.05 GW is energized. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Partially energized · Private land · Tenaga Nasional Berhad (TNB) · Kulai, Johor, Malaysia
Capacity: announced vs energized
Announced
0.50 GW
reported
Contracted
not recorded
Under construction
0.30 GW
reported
Energized
0.05 GW
verified
Announced-to-energized gap: 0.45 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
| Source | ||||
|---|---|---|---|---|
| Announced | 0.50 GW | 2025-10-31 | reported | press release |
| Energized | 0.05 GW | 2025-10-31 | verified | journalist report |
| Under construction | 0.30 GW | 2025-10-31 | reported | press release |
The deal
- developer
- YTL Power International / YTL Data Center Holdings · Owner-operator of the 1,640-acre park; runs YTL AI Cloud.
- chip supplier
- Nvidia · Liquid-cooled GB200 NVL72 Grace Blackwell GPUs; strategic partner in the RM10bn project.
- tenant
- YTL AI Cloud · Sovereign/government and citizen AI services host on the first energized facility.
Power
- Power source
- mixed
- Grid operator
- Tenaga Nasional Berhad (TNB)
- Interconnection
Financial structure
- YTL Power - Nvidia AI data center project
- $2.1B. RM10bn YTL Power / Nvidia project at Kulai; part of a broader ~$4.3bn Malaysia buildout reported by DCD. journalist report
Sources
- YTL Power completes first Nvidia-powered AI data centre in Johor, YTL AI Cloud now operational · The Edge Malaysia
- YTL Power completes Nvidia-powered AI data centre in Johor · W.Media
- Nvidia & YTL Power partner for $4.3bn AI data centers in Malaysia · Data Center Dynamics
- YTL Power stamping its mark on DC sector · The Star
6c37130e-35d9-4987-8196-9ab3f0882584 · Tracked with DEPLOY's verified-vs-claimed methodology. Announced numbers are claims, not built capacity.