TeraWulf (NASDAQ: WULF) is a Bitcoin mining company that operates large-scale cryptocurrency mining data centers powered by nuclear and renewable energy.

Founded
2021
HQ
Easton, Maryland, USA
Status
Public

Overview

TeraWulf (NASDAQ: WULF) is a Bitcoin mining company that operates large-scale cryptocurrency mining data centers powered by nuclear and renewable energy. The company's flagship facility is the Lake Mariner Data Center in New York.

Reality check

Controlled power (company-claimed)

Says it controls 2.3 GW for AI and HPC; its homepage metrics also list 2.9 GW controlled and 839 MW contracted.

WULF Compute (company-claimed)

Purpose-built, power-secured, high-density data center campuses for AI and HPC.

Muskie campus (company-claimed)

Oct 2026: Kentucky Power contract raised from 500 MW to 1 GW; phase 1 ramps from 2028, phase 2 moved up from 2030 to 2029. Pending PSC approval.

Bill credits (company-claimed)

Oct 2026 utility filing: if approved, TeraWulf funds $100M in winter bill credits for residential customers over 10 years, about $25 a month in heating season, from 2029.

Business model (company-claimed, Oct 2026)

CEO Paul Prager says TeraWulf is an energy infrastructure company, not a neocloud, and its contracts require investment-grade customers or investment-grade credit support.

Verified record

Verified deployments
None on file
Active incidents
None on file

Key facts

Muskie background

Acquired May 2026; TeraWulf is evaluating up to 2 GW over time. No tenant named.

Revolving credit facility (SEC filing, Oct 2026)

Oct 23 2026: commitments on its Morgan Stanley-agented senior secured revolver rose from $250M to about $400M, with an uncommitted accordion for about $150M more.

Google credit support at Justified (company-stated)

Credit support agreements with Google LLC back debt financing for about $19 billion of contracted Anthropic lease commitments at the Justified Data Campus in Hawesville, Kentucky.

Fluor EPC at Justified (company-stated)

Definitive EPC agreement with Fluor for three data center buildings at Justified. Phased ready-for-service completions are expected from late 2027 through the second quarter of 2028.

Muskie Data Campus utility filings (Kentucky Power, not yet approved)

Kentucky Power filed with the Kentucky PSC on Nov 13, 2026 for approvals to serve TeraWulf's planned Muskie Data Campus in Grayson, up to 1 gigawatt of contracted demand in phases by 2029. PSC decisions could come as early as mid-year 2027.

Data & sources

Press releases

7

Web sources

5

12 sources backing this record.View all →

Partnerships

Every company TeraWulf has built with, alongside the ones only announced in a press release.

3 total2 operating

Most-frequent partners

  1. 1AWS1× joint30 total
  2. 2Fluidstack1× joint3 total
  3. 3Google1× joint22 total

Relationships

Current leadership (2)

Safety record

No incidents on record for TeraWulf.

Only active incidents are counted. Retracted incidents are excluded from this summary but remain reachable at their canonical URLs.

Full safety record: incidents, sourcing, and exposure data →

TeraWulf on the data-center map

Every verified data center TeraWulf operates that has a mapped coordinate (12 total). Filled circles are Tier-2 facilities and Tier-1 campuses under this operator; click any pin to open its record.

TeraWulf data centers (12)

AI data centers TeraWulf operates or is a party to, from the DEPLOY data center registry.

Recent coverage

TeraWulf in third-party press

Mentioned on (3)

Registry pages whose text names TeraWulf.