Data center campus
Meta Talavera de la Reina Data Center Campus (Torrehierro)
Meta Talavera de la Reina Data Center Campus is an AI data center campus developed by Meta Platforms in Toledo (Castilla-La Mancha), Talavera de la Reina. 0.25 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Under construction · Meta Platforms · other · Talavera de la Reina, Toledo (Castilla-La Mancha), Spain
Capacity: announced vs energized
Announced-to-energized gap: 0.25 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
Promised online: 2030. 51 months away. Claimed by Meta / local planning reports (source).
| Source | ||||
|---|---|---|---|---|
| Announced | 0.25 GW | 2024-06-01 | reported | journalist report |
Key facts
Lifecycle
Announced
Energized
Developer
Location
Grid
Announced-to-energized gap
Reported facts
Structured facts sourced from citations already on this record. Each fact traces to a source in the References section below.
- PSI scope / Zarza Networks Meta (primary CLM)
- Castilla-La Mancha's PSI executive summary for Meta Data Center Campus (promoted by Zarza Networks, S.L., with Meta as sole shareholder) describes a ~191 ha gross scope at Torrehierro Fase 2 in Talavera de la Reina, of which ~175.74 ha is unconsolidated industrial urban land. The Consejo de Gobierno definitive PSI approval is dated 14 Oct 2024 (DOCM no. 205, 22 Oct 2024) (CLM urbanismo PSI resumen)
- Private DC parcel / building program (primary CLM)
- The PSI resumen states the Data Center Campus develops inside a discontinuous private parcel of 102 ha with total buildability of 130,000 m2 and a set of permanent buildings totaling 72,705 m2, centered on two data-center buildings plus administrative (ADM), infrastructure business operations support (IBOS), and security gatehouse (GH) buildings. An on-campus HV substation is described as connecting to Redeia's Calera y Chozas substation (CLM urbanismo PSI resumen)
- Investment / construction timeline (primary CLM)
- The PSI resumen estimates total investment for the PSI at around 750 million euros, of which 685 million euros for data-center construction, with construction/edification within a maximum of 10 years from start and the promoter to begin works within 12 months after all administrative processes and approvals are complete (CLM urbanismo PSI resumen)
- Dry-air cooling / LEED / 100% renewable commitments (primary CLM)
- The PSI resumen says the campus is designed around dry-air cooling claimed to cut annual water needs by about 80% versus prior design, commits to LEED certification, states Meta data centers and offices are Net-Zero supported by 100% renewable energy (with a commitment to support renewable generation equal to 100% of campus consumption), and commits to restore more water than the facility consumes via hydrological restoration projects (CLM urbanismo PSI resumen)
- Reparcelation / building-license path (reported Aug-Sep 2026)
- Cadena SER reports that after Fomento's definitive reparcelation approval (resolution 7 Aug 2026, DOCM 21 Aug 2026), Zarza Networks constituted the municipal urban-use monetization guarantee on 2 Sep 2026, which regional officials frame as clearing the path toward municipal building licenses. ABC similarly reports the definitive reparcelation authorization lets Meta present construction projects and seek Ayuntamiento de Talavera licenses, restating the ~750M euro investment figure (and noting some officials say it could exceed 1,000M depending on final buildout; treat that higher figure as reported, not PSI text) (Cadena SER, Sep 5 2026; ABC, Aug 25 2026)
On the data center map
No mappable coordinate is recorded for Meta Talavera de la Reina Data Center Campus (Torrehierro) yet. Location: Talavera de la Reina.
- Announced capex
- $1.1B
- Jobs
- 250 permanent reported
- Cost per MW
- $5M/MW
- Cost per job
- $4M per permanent job
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
The deal
- developer
- Meta Platforms · Developer and operator; Meta's fourth European data center
- utility
- Red Electrica / Redeia · Developing the 220 kV substation at Calera y Chozas
Power
- Power source
- grid
- Grid operator
- other
- Interconnection
220 kV substation at Calera y Chozas (Red Electrica/Redeia), grid, Under construction. Grid interconnection for the campus
Why here
Meta Talavera de la Reina Data Center Campus is in Toledo (Castilla-La Mancha), Talavera de la Reina. It connects to the other grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.
Financial structure
- Meta investment 2024-2030 (~EUR 1.03bn)
- $1.1B journalist report
Investment, workforce and specs
Timeline
- Aug 2026party addedutility: Red Electrica / Redeia
- Oct 2026Current: Under construction
Sources
- Opening water-guzzling datacenter in empty and dry Spain
- Meta Data Center in Talavera de la Reina will be a 1,000 million dollars investment
- Meta Drives Europe's Digital Future from Talavera: What Its Torrehierro Data Center Will Look Like
- PSI Resumen ejecutivo - Meta Data Center Campus (Zarza Networks)
- Nuevo paso para materializar el centro de datos de Meta en Talavera (750M euros)
- Meta ya puede solicitar las licencias de obra para su campus de datos en Talavera
6e1e64cb-aa2a-424b-8dfe-59d1535ae1e9 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Meta Talavera de la Reina Data Center Campus (Torrehierro)?
How much power will Meta Talavera de la Reina Data Center Campus (Torrehierro) use?
Who is building Meta Talavera de la Reina Data Center Campus (Torrehierro)?
Is Meta Talavera de la Reina Data Center Campus (Torrehierro) operating yet?
How verified is the data on Meta Talavera de la Reina Data Center Campus (Torrehierro)?
Deploy Watch
Track Meta Talavera de la Reina Data Center Campus (Torrehierro) on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Meta Talavera de la Reina Data Center Campus (Torrehierro): AI data center campus record. Retrieved October 4, 2026, from https://registry.deploy.report/datacenters/meta-talavera-de-la-reina
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/meta-talavera-de-la-reina.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/meta-talavera-de-la-reina
- Data documentation: /data
- Query this programmatically: Deploy MCP