Data center campus
Cayuga Data Campus
Cayuga Data Campus is an announced AI data center campus. 0.40 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Announced · Former industrial site · NYISO · Lansing, New York, United States
Capacity: announced vs energized
Announced
0.40 GW
verified
Contracted
not recorded
Under construction
0.14 GW
reported
Energized
not recorded
Announced-to-energized gap: 0.40 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
| Source | ||||
|---|---|---|---|---|
| Announced | 0.40 GW | 2026-03-31 | verified | sec filing |
| Under construction | 0.14 GW | 2026-02-26 | reported | earnings call |
The deal
- developer
- TeraWulf Inc. · NASDAQ: WULF; 80-year site lease
- utility
- NYISO
Power
- Power source
- grid
- Grid operator
- NYISO
- Interconnection
Sources
- TeraWulf Inc. Form 10-Q (period ended March 31, 2026)
- TeraWulf Reports Fourth Quarter and Full Year 2025 Results
bfb3c5e7-fd63-4901-a271-d8a1a11aa7ba · Tracked with DEPLOY's verified-vs-claimed methodology. Announced numbers are claims, not built capacity.