Data center campus

Microsoft Fairwater Data Center (Mount Pleasant)

Microsoft Fairwater Data Center is an announced AI data center campus. 0.45 GW of capacity has been announced; 0.37 GW is energized. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Partially energized · Former industrial site · MISO · Mount Pleasant, Wisconsin, United States


Capacity: announced vs energized

Announced
0.45 GW
reported
Contracted
not recorded
Under construction
2.26 GW
claimed
Energized
0.37 GW
reported

Announced-to-energized gap: 0.08 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Microsoft Fairwater Data Center (Mount Pleasant) capacity claims
Source
Announced0.45 GW2025-01-01reportedutility filing
Energized0.37 GW2026-04-16reportedjournalist report
Under construction2.26 GW2028-05-13claimedjournalist report

The deal

developer
Microsoft · Owner-operator; Fairwater flagship AI datacenter on former Foxconn land.
tenant
Microsoft / OpenAI · Self-tenant AI supercompute (Azure).
chip supplier
NVIDIA · GB200/B200-class GPUs (Epoch cites B200).
utility
We Energies · Regulated monopoly; sole grid power supplier, building new gas generation.
grid operator
MISO · We Energies operates within MISO.

Power

Power source
grid
Grid operator
MISO
Interconnection

We Energies Oak Creek gas plant (5 simple-cycle turbines), 1.10 GW gas, Permitted. 1,100 MW proposed at the Oak Creek coal site; first turbine delivery May 2026, operations winter 2027-summer 2028.

We Energies Paris gas plant (Kenosha County), 0.13 GW gas, Permitted. 128 MW gas plant near Paris, WI; part of ~$2.77B of PSC-approved generation/transmission justified on Microsoft load.

Financial structure

Microsoft Mount Pleasant campus investment (announced)
$3.3B. Initial announced investment; Epoch estimates ~$14B deployed to date and ~$85B at full buildout. press release

Sources

824d3b90-2903-4335-9716-8f73fb969f7a · Tracked with DEPLOY's verified-vs-claimed methodology. Announced numbers are claims, not built capacity.