QTS Phoenix 3 Campus (Glendale)

QTS Phoenix 3 Campus is an announced AI data center campus. 0.75 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Permitted · Private land · WECC · Glendale, Arizona, United States


Capacity: announced vs energized

Announced
0.75 GW
reported
Contracted
not recorded
Under construction
not recorded
Energized
not recorded

Announced-to-energized gap: 0.75 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

QTS Phoenix 3 Campus (Glendale) capacity claims
Source
Announced0.75 GW2023-01-01reportedcounty docket

The deal

developer
QTS Data Centers · Owned by Blackstone.
financier
Blackstone
utility
Arizona Public Service (APS) · Glendale/Loop 303 corridor; service agreement not confirmed.

Power

Power source
grid
Grid operator
WECC
Interconnection

On-site ~29-acre substation, 0.75 GW grid interconnect, Announced. Dedicated substation planned to serve the campus.

Sources

65cc65ec-d466-4830-a24f-34926a4a9436 · Tracked with DEPLOY's verified-vs-claimed methodology. Announced numbers are claims, not built capacity.