Data center campus
EdgeCore Mesa (North Campus, Elliot Road Technology Corridor)
EdgeCore Mesa is an AI data center campus developed by EdgeCore Digital Infrastructure in Arizona, Mesa. 0.45 GW of capacity has been announced; 0.21 GW is energized. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Permitted · EdgeCore Digital Infrastructure · Private land · WECC · Mesa, Arizona, United States
Capacity: announced vs energized
Announced-to-energized gap: 0.24 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
Promised online: 2026. Energized capacity is now on record. Claimed by EdgeCore Digital Infrastructure (source).
| Source | ||||
|---|---|---|---|---|
| Announced | 0.45 GW | 2025-05-21 | reported | county docket |
| Energized | 0.21 GW | 2025-05-20 | verified | company filing |
Key facts
Lifecycle
Announced
Energized
EdgeCore Digital Infrastructure
Developer
Location
Grid
Land
Announced-to-energized gap
Reported facts
Structured facts sourced from citations already on this record. Each fact traces to a source in the References section below.
- 450 MW+ Metro Phoenix expansion / land (primary EdgeCore)
- On May 20, 2025 EdgeCore Digital Infrastructure announced acquisition of an additional 43.87 acres in Mesa and expanded capacity designed to deliver 450 MW+ to hyperscale customers, stating the parcel more than doubles buildable acreage EdgeCore controls in Mesa. CEO Lee Kestler said that since establishing the first Mesa campus in April 2023 the company had constructed and commissioned 206 MW at the site, and that the new land enables another 250+ MW of data center space (EdgeCore, May 20 2025)
- SRP power delivery timing (primary EdgeCore)
- EdgeCore states affordable power via Salt River Project (SRP) is already available at its first Mesa campus for the operational data center and is slated for delivery to two buildings under construction upon completion in 2025 and 2026. SRP GM/CEO Jim Pratt is quoted congratulating the expansion and noting EdgeCore's water-conservation commitment (EdgeCore, May 20 2025)
- Air-cooled design / certifications (primary EdgeCore)
- EdgeCore describes Mesa data centers as air-cooled with an ultra-efficient closed-loop chilled water system requiring nearly no water to recharge, designed to meet LEED BD+C v4 Silver standards, with PH01 receiving Green Globes for Existing Buildings certification in 2023 and PH02/PH03 (under construction at announcement) awarded Designed to Earn ENERGY STAR certifications (EdgeCore, May 20 2025)
On the data center map
Every tracked data center is on this map, centered on EdgeCore Mesa. Pan or zoom out to see how close rivals are building.
In clusterArizona(149)
The deal
- developer
- EdgeCore Digital Infrastructure
- utility
- Salt River Project (SRP) · Mesa/Eastmark corridor; specific service agreement not confirmed.
Power
- Power source
- grid
- Grid operator
- WECC
- Interconnection
County water status: Extreme drought (D3) in Maricopa County, week of 2026-09-29 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Why here
EdgeCore Mesa sits on private land in Arizona, Mesa. It connects to the WECC grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Timeline
- Aug 2026capacity changedenergized: unknown to 0.206
- Oct 2026Current: Permitted
Sources
- EdgeCore's massive data center campus in Mesa clears checkpoint
- EdgeCore expands Mesa data center campus in Arizona
- EdgeCore Digital Infrastructure Announces Expansion of Its Metro Phoenix Data Center Market to Over 450 MW
1f2bbec1-0b76-46f4-a5c6-6eb2a61ee986 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is EdgeCore Mesa (North Campus, Elliot Road Technology Corridor)?
How much power will EdgeCore Mesa (North Campus, Elliot Road Technology Corridor) use?
Who is building EdgeCore Mesa (North Campus, Elliot Road Technology Corridor)?
Is EdgeCore Mesa (North Campus, Elliot Road Technology Corridor) operating yet?
How verified is the data on EdgeCore Mesa (North Campus, Elliot Road Technology Corridor)?
Deploy Watch
Track EdgeCore Mesa (North Campus, Elliot Road Technology Corridor) on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). EdgeCore Mesa (North Campus, Elliot Road Technology Corridor): AI data center campus record. Retrieved October 2, 2026, from https://registry.deploy.report/datacenters/edgecore-mesa-north-campus
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/edgecore-mesa-north-campus.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/edgecore-mesa-north-campus
- Data documentation: /data
- Query this programmatically: Deploy MCP