Data center campus
Crusoe Abilene AI Data Center (Stargate Site 1)
Crusoe Abilene AI Data Center is a tracked AI data center campus in Texas, Abilene. Anchor site for the OpenAI/Oracle Stargate program; Crusoe develops and operates, Oracle leases and subleases to OpenAI. NVIDIA GB200 NVL72 deployed at scale.
Partially energized · Crusoe · ERCOT · Abilene, Texas, United States
Capacity: announced vs energized
| Source |
|---|
Key facts
Lifecycle
Energized
Developer
Location
Grid
Facilities tracked
Reported facts
Structured facts sourced from citations already on this record. Each fact traces to a source in the References section below.
- IT capacity
- 1200 MW (Public reporting: 8 buildings, ~1.2 GW at full buildout; first two buildings energized 2025)
- Grid operator
- ERCOT
- Serving utility
- Oncor / AEP
On the data center map
Every tracked data center is on this map, centered on Crusoe Abilene AI Data Center. Pan or zoom out to see how close rivals are building.
In clusterTexas(606)
The deal
- developer
- Crusoe
Power
- Power source
- grid
- Grid operator
- ERCOT
- Interconnection
The Texas (ERCOT) grid demand right now: 63.1 GW (EIA-930, 2026-08-29 15:00).
County water status: Moderate drought (D1) in Taylor County, week of 2026-08-25 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Why here
Crusoe Abilene AI Data Center is in Texas, Abilene. It connects to the ERCOT grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.
Regulatory paper trail
The filings and rules on record for this site and its jurisdiction, most recent first. Each is a sourced, dated artifact you can follow to the primary document.
Facilities at this campus
Sources
23fecf27-e478-410e-8275-81276364220c · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is Crusoe Abilene AI Data Center (Stargate Site 1)?
Who is building Crusoe Abilene AI Data Center (Stargate Site 1)?
Is Crusoe Abilene AI Data Center (Stargate Site 1) operating yet?
How verified is the data on Crusoe Abilene AI Data Center (Stargate Site 1)?
Deploy Watch
Track Crusoe Abilene AI Data Center (Stargate Site 1) on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). Crusoe Abilene AI Data Center (Stargate Site 1): AI data center campus record. Retrieved August 29, 2026, from https://registry.deploy.report/datacenters/crusoe-abilene-ai-data-center
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/crusoe-abilene-ai-data-center.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/crusoe-abilene-ai-data-center
- Data documentation: /data