Data center campus
EdgeConneX Cedar Creek Campus (CoreWeave AUS02)
EdgeConneX Cedar Creek Campus is an AI data center campus developed by EdgeConneX in Texas, Bastrop. 0.10 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Under construction · EdgeConneX · Private land · ERCOT · Cedar Creek, Bastrop, Texas, United States
Capacity: announced vs energized
Announced-to-energized gap: 0.10 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
Expected online: August 1, 2026. 4 months past the claimed date, with no energized capacity on record..
| Source | ||||
|---|---|---|---|---|
| Announced | 0.10 GW | 2025-04-01 | claimed | company |
Key facts
Lifecycle
Announced
Energized
Developer
Location
Grid
Land
Announced-to-energized gap
Reported facts
Structured facts sourced from citations already on this record. Each fact traces to a source in the References section below.
- Developer / landlord
- EdgeConneX
- Named occupant (Building 1)
- CoreWeave
- Location
- 6752 FM 535, Cedar Creek, Bastrop County, Texas
- Timeline (sources differ)
- First building to open Aug 2026 per local press; first phase by 2027 per EdgeConneX
- Power phasing (company-claimed)
- AUS01 96 MW first building on 130 acres; Austin sites total 240 MW
- Building 1 cost (reported)
- About $440 million
- Tax treatment
- Bastrop County 10-year 75% abatement (Dec 2024), assigned to CoreWeave Oct 2025
- Campus scope (reported)
- Up to 19 potential buildings across Cedar Creek sites; Wolf Lane campus planned for four
- Building naming (sources differ)
- EdgeConneX calls the site AUS01; press calls the CoreWeave building AUS02
On the data center map
Every tracked data center is on this map, centered on EdgeConneX Cedar Creek Campus. Pan or zoom out to see how close rivals are building.
Approximate pin. We hold a city-level coordinate for this campus, not a verified site coordinate, so the marker shows the city rather than the parcel. The satellite strip and building outlines stay off until the site coordinate is sourced.
- Announced capex
- $440M
- Cooling
- closed-loop (local reporting for Cedar Creek EdgeConneX facilities)
- Grid
- ERCOT · due 2026
- Tenant
- CoreWeave
- Cost per MW
- $5M/MW
Every figure is one row in the ledger below with its source. Derived rows are pure arithmetic on the rows above (not new claims). Absent lines mean the fact isn't on record yet.
In clusterBastrop(7)·Texas(611)
The deal
- developer
- EdgeConneX · Campus developer / landlord for the Cedar Creek multi-building project.
- tenant
- CoreWeave · Named qualifying occupant of Building 1 in Texas/county records per Community Impact.
- grid operator
- ERCOT · Campus sits in the ERCOT footprint (registry gridOperator).
Power
- Power source
- grid
- Grid operator
- ERCOT
- Interconnection
- Water
- Local reporting says Cedar Creek EdgeConneX facilities are expected to use closed-loop cooling designed to reduce water consumption ([Texas Reporter](https://texreporter.com/2026/09/02/four-cedar-creek-data-centers-represent-2-8-billion-development/)).
The Texas (ERCOT) grid demand right now: 50.6 GW (EIA-930, 2026-11-07 05:00). EdgeConneX Cedar Creek Campus's announced 0.10 GW would be 0.2% of the grid's current load.
County water status: Severe drought (D2) in Bastrop County, week of 2026-11-17 (US Drought Monitor). Data centers are large water users for cooling; this is the neutral local water picture.
Why here
EdgeConneX Cedar Creek Campus sits on private land in Texas, Bastrop. It connects to the ERCOT grid, draws on grid power. This siting summary is composed from the record's held fields, not speculation; see methodology.
Financial structure
- Building 1 estimated project cost (reported)
- $440M. Community Impact / DCD: ~$440M estimated cost for the first Cedar Creek building associated with CoreWeave occupancy. journalist report
Regulatory paper trail
The permits, filings and rules on record for this site and its jurisdiction. Each is a sourced, dated artifact you can follow to the primary document.
Investment, workforce and specs
Timeline
- Sep 2026party addedgrid_operator: ERCOT
- Nov 2026Current: Under construction
Sources
- AI cloud company CoreWeave to fill $440M Cedar Creek data center · Community Impact
- EdgeConneX Austin Data Center | Colocation & Connectivity · EdgeConneX
- EdgeConneX Austin Data Sheet (April 2025) · EdgeConneX
- CoreWeave to lease capacity from EdgeConneX at data center campus in Cedar Creek, Texas · Data Center Dynamics
- Four Cedar Creek data centers represent $2.8 billion development · Texas Reporter
e5d8beeb-01ca-44d3-a044-c1d6ae9fcfe9 · Tracked with DEPLOY's verified-vs-claimed methodology. Every term is defined in the glossary. Announced numbers are claims, not built capacity.
Head-to-head
Common questions
What is EdgeConneX Cedar Creek Campus (CoreWeave AUS02)?
How much power will EdgeConneX Cedar Creek Campus (CoreWeave AUS02) use?
Who is building EdgeConneX Cedar Creek Campus (CoreWeave AUS02)?
Is EdgeConneX Cedar Creek Campus (CoreWeave AUS02) operating yet?
How verified is the data on EdgeConneX Cedar Creek Campus (CoreWeave AUS02)?
Deploy Watch
Track EdgeConneX Cedar Creek Campus (CoreWeave AUS02) on Deploy.
We notify you when energized capacity, lifecycle state, or a new dated capacity claim changes against primary-source evidence, not when the developer issues a press release.
Cite this page
DEPLOY. (2026). EdgeConneX Cedar Creek Campus (CoreWeave AUS02): AI data center campus record. Retrieved November 20, 2026, from https://registry.deploy.report/datacenters/edgeconnex-cedar-creek-texas
More citation formats (MLA, Chicago, BibTeX) →The verified data on this page is available under a Creative Commons Attribution 4.0 license: reuse the facts freely, with attribution to DEPLOY (deploy.report). The prose, design, and any imagery are not included and keep their own rights.
Machine-readable surfaces
- Markdown mirror: /datacenters/edgeconnex-cedar-creek-texas.md
- JSON-LD: embedded in this page’s head
- REST API: /v1/datacenters/edgeconnex-cedar-creek-texas
- Data documentation: /data
- Query this programmatically: Deploy MCP