Data center campus

Data City (Energy Abundance)

Data City is an announced AI data center campus. 5 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Announced · greenfield · ERCOT · Laredo, Texas, United States


Capacity: announced vs energized

Announced
5 GW
claimed
Contracted
not recorded
Under construction
not recorded
Energized
not recorded

Announced-to-energized gap: 5 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Data City (Energy Abundance) capacity claims
Source
Announced5 GW2025-04-07claimedpress release

The deal

developer
Energy Abundance Development Corporation

Power

Power source
mixed
Grid operator
ERCOT
Interconnection

Data City on-site generation, solar, Announced. Wind + solar + battery + dual-fuel gas turbines to hydrogen; capacities not itemized

Sources

a6b4ec9e-0a60-4e81-92a2-cbd514edd057 · Tracked with DEPLOY's verified-vs-claimed methodology. Announced numbers are claims, not built capacity.