Data center campus
Alpha Digital Campus (LandBridge / PowerBridge)
Alpha Digital Campus is an announced AI data center campus. 2 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Announced · Private land · ERCOT · Pecos, Texas, United States
Capacity: announced vs energized
Announced
2 GW
reported
Contracted
not recorded
Under construction
not recorded
Energized
not recorded
Announced-to-energized gap: 2 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
| Source | ||||
|---|---|---|---|---|
| Announced | 2 GW | 2026-04-02 | reported | utility filing |
The deal
- developer
- PowerBridge · Power + data-center developer
- financier
- LandBridge Company (NYSE: LB) · Surface-land owner/lessor
Power
- Power source
- behind the meter gas
- Grid operator
- ERCOT
- Interconnection
Alpha Digital co-located generation, 2 GW gas, Announced. Co-located gas generation near Waha hub
Sources
- LandBridge Announces Agreement with PowerBridge for the Development of a 2 GW Powered Data Center Campus
- LandBridge & PowerBridge partner for 2GW data center campus in West Texas
88a8d36e-a461-4d72-be47-0deb84cdb9d9 · Tracked with DEPLOY's verified-vs-claimed methodology. Announced numbers are claims, not built capacity.