Data center campus

Sandow Lakes Power / Data Center Campus

Sandow Lakes Power / Data Center Campus is an announced AI data center campus. 1.20 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Under construction · Former industrial site · ERCOT · Blue, Texas, United States


Capacity: announced vs energized

Announced
1.20 GW
reported
Contracted
not recorded
Under construction
not recorded
Energized
not recorded

Announced-to-energized gap: 1.20 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Sandow Lakes Power / Data Center Campus capacity claims
Source
Announced1.20 GW2025-10-01reportedpermit

The deal

developer
Sandow Lakes Energy Company · Owns power plant via subsidiary
operator
Gemma Power Systems (Argan Inc.) · EPC contractor

Power

Power source
behind the meter gas
Grid operator
ERCOT
Interconnection

Sandow Lakes Power Plant, 1.20 GW gas, Under construction. TCEQ air permit issued Oct 2025; Gemma/Argan NTP

Sources

b26697a8-cfa3-4c44-9aa4-b37e912d9536 · Tracked with DEPLOY's verified-vs-claimed methodology. Announced numbers are claims, not built capacity.