Data center campus
Lancium Fort Stockton Clean Campus
Lancium Fort Stockton Clean Campus is an announced AI data center campus. 0.33 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.
Partially energized · greenfield · ERCOT · Fort Stockton, Texas, United States
Capacity: announced vs energized
Announced-to-energized gap: 0.33 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.
| Source | ||||
|---|---|---|---|---|
| Announced | 0.33 GW | 2022-11-01 | reported | utility filing |
The deal
- operator
- Lancium · Blackstone-backed (~$500M investment reported)
- utility
- ERCOT · Controllable Load Resource designation Nov 2022
Power
- Power source
- grid
- Grid operator
- ERCOT
- Interconnection
ERCOT grid interconnection (Controllable Load Resource), 0.33 GW grid interconnect, Partially energized. Lancium Smart Response demand-flexibility; designated CLR by ERCOT
Sources
- Lancium Breaks Ground On First Clean Campus In Fort Stockton, Texas
- Fort Stockton Clean Campus
- Fort Stockton Clean Campus Data Center (325 MW)
a91b1386-c93a-4a94-b298-767521f80726 · Tracked with DEPLOY's verified-vs-claimed methodology. Announced numbers are claims, not built capacity.