Crusoe Childress Campus

Crusoe Childress Campus is an announced AI data center campus. 1.40 GW of capacity has been announced; none is energized yet. The gap is what this page tracks: what is claimed versus what is actually built, each figure dated and sourced.

Announced · Private land · ERCOT · Childress, Texas, United States


Capacity: announced vs energized

Announced
1.40 GW
claimed
Contracted
not recorded
Under construction
not recorded
Energized
0 GW
reported

Announced-to-energized gap: 1.40 GW. Every figure below is a single dated, sourced claim. Current best per series resolves by evidence tier, then date. See the methodology.

Crusoe Childress Campus capacity claims
Source
Announced1.40 GW2026-07-15claimedjournalist report
Energized0 GW2026-07-15reportedjournalist report

The deal

developer
Crusoe Energy · Develops and operates the data center campus.
utility
Lancium · Owns the 270-acre site and develops/manages behind-the-meter energy infrastructure.
grid operator
ERCOT · 1 GW interconnect fully approved by ERCOT.

Power

Power source
solar storage
Grid operator
ERCOT
Interconnection

Behind-the-meter solar + battery storage (Lancium), solar storage, Announced. Lancium develops/manages behind-the-meter solar and storage; specific generation capacity not disclosed. 1 GW ERCOT-approved grid interconnect.

Sources

405e9627-7a7b-4bf2-8ae1-275248cdb27e · Tracked with DEPLOY's verified-vs-claimed methodology. Announced numbers are claims, not built capacity.